August 10th, 2012
Final Touches
August 1st, 2012
Bleachers Done, Track Surface Work,
Final Touches
July 17th, 2012
Bleacher Installation begun, First Test of Lights,
Fencing and other work

Several dozen players, coaches and fans were on
hand for
the inaugural test of the stadium lights.
|

Not a single dark spot was found on the field |

Bringing power to the stadium
|
 |

Bleachers going in |

These are the foot rests going in first, then the
seats
|

|
 |

Scoreboard - Done!! |

Play Clock - Done!!
|

|
 |

Sound System behind
the Scoreboard
|

Working on fencing
around the stadium |

Work on the Stadium
Entrance, the old stadium rock pillars will be
recreated and the same Jerry Litton Stadium
Entrance sign will be used
|

|

One of the Throws Pits (notice two different
locations)
|

Looking across the field |

Views from Highway 65 |
 |
July 10th, 2012
|
June 24th, 2012 |

First Floor of Press Box, looking North |

Second Floor of Press Box, looking South
|

Location of the
"Redneck Parking Lot"
(or, as I like to refer to it, the "Parking Lot
Posse").
Spaces will be sold, right behind the opposing
team bench, because opposing coaches really loved
this little feature at the old stadium so much.
|

|

Looking Southwest |

Locker Room, looking
from next to the Press Box
|

Press Box on left,
Restroom Entrances on Right
Looking South |

Press box on Right,
Concession Stand on left
Looking North
|

Restroom on Left
|

Restroom on Right |

View from the Press
Box. |

|

|

|

Concession Stand |

Looking in from the rear of the Concession Stand
|

|

Looking Southwest,
locker room building
|
 |
 |
|
|
Shot Put and Discus
area, located East of the field, behind the
"Redneck Parking Lot". Notice there are two sets
of throwing pits, one set on the bottom of the
picture, and one set near the top of the picture.
|

Looking Northwest |

Bonus points for your
throw landing in the pond, perhaps? |
Press
Box Construction Begins
June 12th, 2012

Grass seed on North end of Stadium
|

Framing underway on
first floor of Press box
|

Framing underway
on first floor, second floor framing next |

Restrooms Right Behind Press Box. Excellent Idea!
|
 |
 |
Work
Progressing
May 31st, 2012
Turf
Almost Done, Locker Room Interior Work
May 20th, 2012
Installing
the Turf, Work on the Locker Rooms
May 10th, 2012

Turf is
going down, end zones will be red, every five
yards
will alternate dark green with light green. Individual yard
markers and center field emblem design not yet added.
New Goal Posts are installed |

|

|
 |

New Locker Room Building, located on the south end
of the stadium. |

|

|
 |
 |
 |
Prepping
for Turf, Building Foundations and Plumbing
April 25, 2012 |